More power, lower cost, one connection: Guruve-Mazowe, Zimbabwe

Converge Hybrid

converge-hybrid.com

Case study: hybrid renewable energy in Zimbabwe

More power, lower cost, one connection

How Tatanga Energy’s five years of groundwork, and a hybrid design developed with Modaso on the Converge Hybrid platform, became one of Zimbabwe’s most significant planned energy investments.

“As a wind-only project, it was probably on the borderline of whether it would be financeable or not.”

Charles HaworthCo-founder of Converge Hybrid and Modaso Energy

The same grid connection, almost twice the power

How much of the year each design keeps the connection working, as modelled on the Converge Hybrid platform.

Wind onlyThe original 100 MW design
HybridWind, solar and battery
  • Wind
  • Solar
  • Battery

Modelled capacity factor: the share of the connection’s full capacity used across a year. The split of the hybrid bar between wind, solar and battery is illustrative.

  • 128 MWWind
  • 100 MWacSolar
  • 100 MWhBattery storage, 50 MW
  • ~550 GWhA year, about 5% of Zimbabwe’s generation
  • ~$300mPlanned capital investment
  • Six monthsFrom agreement to announcement

As announced by Modaso Energy and Tatanga Energy, 3 November 2026. Output figures are expected, not measured.

01 / The challenge

Strong foundations, a hard market

The Guruve-Mazowe project began as a wind farm. Over around five years, Tatanga Energy, a Zimbabwean developer, built the foundations that every later decision rested on: it identified the site in Mashonaland Central, secured the land, and ran a wind measurement campaign from 2021.

That groundwork is what made the project attractive. Jerome Niessen, a development director at Modaso Energy who had worked with Tatanga for several years, introduced it to Modaso, and the due diligence confirmed its strengths: four to five years of measured wind data, secured land and a high-voltage transmission line running right alongside the site. Without that foundation, no hybrid design would have been possible.

The difficulty lay in how little of the time the project would use that line. As a wind farm, its modelled capacity factor was around 35%, meaning that over a year it would generate about a third of what it could if it ran at full output continuously. To recover its costs, a wind-only project would need a relatively high price for its electricity, and securing that price was a challenge in the current market for any wind-only project.

Those economics matter more in Africa than almost anywhere. Around 600 million people across the continent live without reliable electricity, yet it has some of the world’s best wind and solar resources, and in many countries the grid already exists but is under-used. Yet because investors perceive African projects as riskier, they expect higher returns than elsewhere, so a project that is marginal on paper rarely gets built. The question for the partners was whether the same site, on the same line, could deliver more.

Aerial view of a large solar farm with a block of battery storage units beside it, set in dry scrubland
Solar and battery storage side by side: two of the three technologies in a hybrid design. Photo: Modaso Energy

02 / The breakthrough

Hundreds of designs, one connection

Across the industry, a good wind site is still usually developed as a wind farm. Wind is well understood, and the tools most developers use assess one technology at a time. A hybrid is far harder to conceive, because everything interacts. That is why every opportunity that reaches Modaso is modelled on the Converge Hybrid platform first; Charles uses it daily.

Wind and solar produce at different times of day, a battery can shift energy between them, and tariffs, hourly prices and grid limits all change which combination works best. A conventional study compares three or four scenarios in spreadsheets, with energy and finances often modelled in separate tools. The platform holds technical and commercial results in one model, so pulling a lever on one side shows its effect on the other immediately.

“There’s so many levers to pull, it’s very hard to know if you’ve actually got the optimum setup.”
Charles Haworth
25507510003:0006:0009:0015:0018:0021:00MidnightNoonWind
Wind aloneFossil fuels supply 44% of the day’s 100 MW
25507510003:0006:0009:0015:0018:0021:00MidnightNoonHybrid
Hybrid: wind, solar and batteryFossil fuels supply 18%: solar covers the day, the battery the evening
  • 100 MW supply, as modelled
  • Wind
  • Solar
  • Battery
  • Battery charging
  • Fossil fuels
  • Curtailed

A typical spring day, 1 November, hour by hour, modelled on the Converge Hybrid platform for Guruve-Mazowe. Both clocks use the same wind farm and the same wind; the hybrid adds solar and the battery. Rings mark 25, 50, 75 and 100 MW. The model asks the plant to supply a flat 100 MW every hour, and any shortfall is shown as fossil fuels.

  1. Step 1Import

    The wind and solar resource, with the site’s land, grid and road access.

  2. Step 2Configure

    Equipment options and costs, the power prices on offer and the grid’s limits.

  3. Step 3Simulate

    Every hour of a 25 to 30 year life, with intelligent dispatch deciding what the battery does each hour, as a real operator would.

  4. Step 4Optimise

    Hundreds or thousands of designs, each with full 30-year financials, filtered against capacity factor or a hurdle rate of return.

  5. Step 5Sculpt

    The strongest design taken back into detail and refined with offtakers and partners.

Import → Configure → Simulate → Optimise → Sculpt

Simulate: a week of dispatch, hour by hour

00%2525%5050%7575%100100%Tue 29 OctWed 30 OctThu 31 OctFri 01 NovSat 02 NovSun 03 NovMon 04 NovMWBattery
  • Wind
  • Solar
  • Battery
  • Fossil fuels
  • Battery charge
Guruve-Mazowe, 29 October to 4 November, modelled on the Converge Hybrid platform.

The menu pointed to hybrid

For Guruve-Mazowe, the sweep pointed clearly to hybridisation, and the partners agreed a design that expanded the wind installation, added about 100 MW of solar on adjacent land and incorporated a 100 MWh battery. Together they lift the modelled capacity factor to around 65%, almost double the power down the same line, with no new substation capacity or transmission.

The project’s fixed costs of financing, development and operation are now spread across far more energy and revenue, so the cost of each megawatt hour falls. In Modaso’s assessment, the hybrid design was bankable where wind alone had been borderline.

“It really gives you a menu of options.”
Charles Haworth
Chosen designWind MWSolar MWProject value
Each dot is one modelled plant design, plotted by wind and solar capacity and project value.

“It’s completely counterintuitive in many cases. Every site is different.” Charles Haworth, who has modelled renewable projects for 20 years.

03 / Making it financeable

Answers to the three questions every lender asks

The hybrid design was the beginning, not the end. The partners had to secure additional land from neighbouring farmers, revise the layout and reapply for environmental permits. Above all, they had to answer the questions on which every financing decision rests, and the platform helped with each.

Who will buy the power?

In mature markets, a renewable project typically sells all its output to a government utility at a fixed price. In Zimbabwe, Modaso had to be more creative, and the project has three routes to market.

Trading on a day-ahead market is unusual for a renewable project. Using hourly price data, the platform showed when power is most valuable, typically 6–8am and 6–8pm as solar drops away, so the design and the battery could be shaped to serve those peaks while meeting contracted supply.

What happens in the downside case?

Lenders size their debt on a cautious estimate known as P90: the annual output a project has a 90% probability of exceeding. For a wind farm, a consultant supplies it routinely. Sitting in front of the bank, the Modaso team realised they could not, because in a hybrid the wind and solar offset each other and the battery moves energy through the day.

Philippe Chabarot and the Converge Hybrid team quickly developed a methodology built on practices the banks already accept, run through the platform. It now sits at the core of how the project’s debt is sized.

“Normally, that’s a super straightforward answer.”

Who will provide the finance?

Standard Bank stepped in early and has signed a mandate to arrange the project’s debt financing.

That gives the partners confidence that projects of this kind can be financed in the market. The financing itself remains subject to due diligence and financial close.

Guruve-MazoweWind, solar and battery behind one grid connection
  • Africa GreenCoPower aggregator for industrial customers, including mines and smelters. Heads of terms signed.
  • ZESAThe national utility: grid connection and demand from homes and industry.
  • Southern African Power PoolDay-ahead trading with Zambia, Botswana, South Africa, Mozambique, Namibia and others.

Real problems make a better platform

This is where the relationship between the two companies shows its value. Modaso meets real development problems every day. The Converge Hybrid team, built by people with around 140 years of combined experience in renewable energy rather than by software generalists, turns those problems into platform capabilities.

Intelligent dispatch, the P90 methodology, developer-ready reports and pro forma financial models all came about this way. Each project sharpens the platform for the next.

A large team in hard hats and high-visibility vests gathered beside a red lattice wind measurement mast
The team on site, beside a wind measurement mast. Photo: Modaso Energy

04 / The progress

Six months that changed the project’s prospects

  1. 2021Tatanga begins measuring the wind at Guruve-Mazowe
  2. June 2026Modaso and Tatanga sign their joint development agreement
  3. November 2026Project announced and presented at the Zimbabwe-Zambia Energy Projects Summit, Livingstone

At the summit, the partners announced the project alongside its prospective offtakers, financing partners, the national utility and the government. The planned investment is nearly $300 million.

If completed, Guruve-Mazowe is expected to be Zimbabwe’s first wind farm and first full hybrid renewable project, and one of the largest infrastructure investments in the country. Its turbines will be vast: Charles compares modern turbines in scale to the Eiffel Tower.

There is still work to do. Over the coming months, the partners must bring every part of the project to international financing standards, finalise the power purchase agreements and raise the debt and equity, with financial close the next milestone. The six months were only possible because of the five years before them. Together, the partners turned that foundation into a proposition that buyers, lenders and government were prepared to announce alongside them.

Two workers in high-visibility vests haul a line skywards on a hilltop, with a third holding a rope behind them and wooded hills beyond
Photo: Modaso Energy
Aerial view of a hybrid renewable site: wind turbines along a ridge, solar arrays on the plain below, and open farmland stretching to the hills
The scale of a hybrid site: wind along the ridge, solar on the plain below. Photo: Modaso Energy

05 / The wider opportunity

The first of many

Guruve-Mazowe is Modaso’s flagship, with further hybrid projects following in Zambia and Kenya and a long-term aim of gigawatts of reliable, low-cost power across Africa.

For the 600 million people still without reliable electricity, the opportunity is not only new grids but better use of the grids that already exist. Hybrid projects put more power down the same lines at a lower cost. The same logic applies far beyond Africa, wherever grids are congested and connections sit idle for much of the year.

600m

people in Africa without reliable electricity

Up to 10 years

in the queue for a grid connection in Germany

30–35%

typical capacity factor of Europe’s wind fleet, leaving its connections unused around 70% of the time

Adding solar and batteries to existing sites, without touching the turbines, could release large amounts of new power without a single new line. None of this asks renewables to do everything alone. Designing for the one windless, sunless week of the year drives costs out of reach. Hybrids can carry the great majority of the load affordably, with hydro, geothermal, existing thermal plant or traded power covering the rest.

“Decarbonisation is a useful side effect of what we’re doing with hybrid renewables. The real story is that countries want more power, more cheaply, and they want it to be homegrown.”
Charles Haworth

More power, lower cost, one connection

More power.

The same 100 MW connection works around 65% of the year, rather than around a third.

Lower cost.

The costs of finance, development and operation are spread across far more energy, so each megawatt hour costs less.

One connection.

No new substation and no new lines. Where grid connections are scarce, slow to secure and expensive to build, that may be the biggest gain of all.

Guruve-Mazowe is one project. The thinking behind it applies wherever a grid connection carries less than it could, and Charles believes that is true anywhere in the world.

Portrait of Charles Haworth

About Charles Haworth

Charles is co-founder and Chairman of Converge Hybrid and co-founder and CTO of Modaso Energy. He grew up on a power station in Nigeria, where his father was a commissioning engineer for GE, and later lived in Lagos and Cairo. After university he joined GE himself, going on to lead commercial teams bidding wind projects in Morocco, Egypt and Kenya.

At CWP Global he worked on gigawatt-scale green hydrogen projects. There, the challenge of delivering stable, high capacity factor power at low cost led him to hybrid design, to Converge Hybrid with Philippe Chabarot and then to Modaso Energy. He has 20 years in renewable energy and has closed billions of dollars of deals.

About Converge Hybrid

Converge Hybrid helps developers, policy makers and their advisers find the right balance of wind, solar and battery storage, turning projects under consideration into solutions that are practical and bankable. Clients can license the platform, engage the consultancy or combine the two.

About Tatanga Energy

Tatanga Energy is a Zimbabwean independent power developer, led by its CEO, Tunde Akerele. It originated the Guruve-Mazowe project and remains the partner on the ground, leading land, community, permitting and government engagement since the wind measurement campaign began in 2021.

Its wider portfolio in Zimbabwe includes the planned Sable solar park at Kwekwe, developed with Sable Chemicals and Masawara, and solar mini-grids for schools and hospitals in Manicaland.

About Modaso Energy

Modaso Energy is the renewable energy company of MISA Group, a Geneva-based investment group. It develops hybrid renewable energy projects across Africa, is led by Ramy Lotfy, Co-Founder and CEO, and Charles Haworth, and applies the Converge Hybrid platform to every project it assesses.

Converge Hybrid’s relationship with Modaso Energy

Modaso Energy is both a client of and an investor in Converge Hybrid. The two companies share a co-founder, Charles Haworth, and work as a mutual partnership: Modaso brings the challenges of real projects, and Converge Hybrid builds the answers into the platform.

Could your project benefit from a different configuration?

Whether you are assessing a new development or reconsidering an existing project, the platform can reveal options that conventional modelling may miss.